Consent Decree – Phase 2

Work in these projects will include Gravity Sewer Line remediation in the form of removing and replacing and/or sliplining cured-in-place pipe (CIPP), and/or pipebursting gravity sewer line in sizes ranging from 8 inch to 54 inch. Manhole remediation for these projects includes selective rehabilitation, entire rehabilitation, replacement or new manhole installation.

Please refer to the City map for the general location of Phase 2 and then the Phase 2 map for locations of the specific projects. The area has been divided into 6 repair and 8 CIPPL construction packages, ranging in construction estimate from $3,000,000 to $13,000,000. Construction will begin first quarter 2018 and all construction for Phase 2 must be complete by May 2019.

Listed below are the current Construction Packages; Designer; Award Amount and Contractor, or Construction Order of Magnitude value.

Please note: Construction starts about three (3) months after Begin Advertising.

To see the type of work scheduled to take place in your neighborhood, click on the numbers (2-101) below. 

REPLACE: Pipes will be replaced using a dig-and-repair method.

CIPP: Pipes will be repaired using trenchless technology to line the existing pipe with minimum excavation.

REASSESS: Pipes will be reassessed for work at a later date.  

PIPE BURST: Another method of trenchless technology where pipes are restored by pulling a new pipe through the older one.

Map Legend

* Information and maps may not be completely up to date, due to varying field conditions and design criteria.

Status Consent Decree Project Numbers & Name Estimated Range & 
Original Contract
Contractor Estimated Timeline
Being Constructed North Highlands Interceptor $3,288,741 Wicker Construction 5/2018 –2/2019
Being Constructed

N. Highlands, Choctaw & Queensboro Sewer Rehabilitation (2-112/123/124/125)

$7,664,744 Suncoast 2/2018 – 2/2019
Being Constructed North Highlands Sewer Replacement (2-123/124) $5,648,710 Wicker Construction 4/2018 – 3/2019
Being Constructed Lift Station Condition Improvements $3,749,015 Belt Construction 6/2018 – 2/2019
Being Constructed North Queensboro Sewer Rehabilitation (2-113/117/122) $6,059,648 PM Construction & Rehab 2/1018 – 1/2019
Being Constructed South Queensboro Sewer Rehabilitation (2-118/119/120/121) $8,267,845 Insituform 1/2018 – 3/2019
Being Constructed Queensboro & Choctaw Bayou Sewer Replacement  $8,528,088 Belt Construction 4/2018 – 2/2019
Being Constructed Westside Sewer Rehabilitation (2-114/115/116) $7,780,133 BLD Services 4/2018 – 3/2019
Being Constructed North Querbes Sewer Rehabilitation (2-102/103/106) $8,159,721 Mitchell Contracting 1/2018 – 3/2019
Being Constructed South Querbes Sewer Rehabilitation (2-101/104/105) $7,108,913 Mitchell Contracting 3/2018 – 3/2019
Being Constructed Westside & Querbes Sewer Replacement 
$1,799,847
Wicker Construction 8/2018 – 2/2019
Being Constructed South Highlands East Sewer Rehabilitation (2-107/109) $7,974,121 PM Construction & Rehab 1/2018 – 2/2019
Being Constructed South Highlands West Sewer Rehabilitation (2-108/110/111) $8,872,853 BLD Services 4/2018 – 3/2019
Being Constructed South Highlands Sewer Replacement (2-107/108/109/110/111) $3,479,189 PM Construction & Rehab 5/2018 – 11/2018
Being Constructed South Querbes Sewer Replacement (2-101/104/105) $1,438,685 PM Construction & Rehab 8/2018 – 12/2018
Being Constructed North Querbes Sewer Replacement (2-102/103/106) $2,880,800 PM Construction & Rehab 8/2018 – 4/2019
Bid & Award Mansfield & Claiborne Area Replacement (2-110/111) $3,146,847 Belt Construction 9/2018 – 3/2019