Drainage Updates

Total for Drainage Projects . . . $12.63M

 

City-wide Drainage
Improvements.....................................................$3.0M




$1 million allocated. Completed Six (6) projects (60” Storm Drain Repair and Cleaning, 7035 Sand Beach BLVD 42” Storm Drain Repair, 1100 BLK. Kelliwood Drainage, 10000 BLK Chase Island Drainage, 1446 Madison Ditch Paving & 8300 BLK. Spring Lake Drainage). Projects under construction: the Greenwood Cemetery Gate House Flood Mitigation, Missouri Ave. & Spruce St. Drainage Replacement & Juniper Place - River Oaks Ditch Improvements. Notice to Proceed issued on 700 Block Delaware Drainage System Repair and Dewberry Drive 30” Pipe Replacement. Design is complete on 8300 Block St. Vincent Avenue Drainage. In Design: Pro and Barbara Drainage Improvements. Initiate other Projects, Design and construct Projects.


 

 

Paved Ditch Repair...........................................$1.7M

 

$600,000 allocated. Completed construction on four phases, Working on the design of other Phases.

 

Purchase of flood prone
properties............................................................$800K

 


$800,000 allocated. Appraisal complete for 1712, 1724, 1717, & 1721 Nash. 4515 Gilbert, 606 Woodmere & 9309 Kildare Park are being considered for acquisition if approved.

 

Juniper Place – River Oaks
ditch improvements............................................$780K

 


$780,000 allocated. Under construction since May 20, 2013. Contractor: Fessler & Bowman.

 

600-700 blk. Browning St.
drainage..............................................................$850K

 


$57,000 allocated. Engineering Contract was executed on 5-23-2012. Surveying work is complete and Design work is in Progress. Completed Preliminary Plans. Final Plans are 95% complete. Project is funded for Design only.


Final Plans are 90% complete. Project is funded for Design only.

 

 

Airport Ditch Repairs........................................$2.5M 

 

 

$2.5 allocated. Bids were opened on June 27, 2013. CW&W Contractors were the apparent low bidder.

 

Ockley Ditch Improvements..............................$3.0M

 

 

$180,200 allocated. Engineering Contract was executed on 5-17-2012, notice to proceed with phase 4 was issued on June 20. Surveying is complete. Issued NTP for Preliminary Plans, Phase 7 on 8-28-2012. Design work is in progress. Final Plans are 90% complete. Project is funded for Design only. Construction and R.O.W. acquisition is pending future bond sales.

 

Last updated: 7/4/13