Streets Updates


   Total for Street projects $31.7M
 

 



 

Sidewalk Repair Program . . $3.0M

 

$1 million allocated. City Engineering working with Council to identify, design, and then contract for repairs

 

Murphy Street Viaduct . . . . .$2.2M

 

Not yet funded. Funding will be made available following sale of remaining bonds

 

Knight Street . . . . . . . . . . . .$3.5M

$288,000 allocated. Project is in design. Construction funding available in second bond sale

 

Traffic Signal System .  .  . . .$2.0M


$146,400 allocated. Prior funding ($2.6 million) allowing design of Phase 1 Kings Hwy to be underway. 




City-wide Street Improvement Program…………………………….$21.0M



Hersey D Wilson




Project is currently under design, to be completed late 2013.  Construction will begin after second bond sale.




 

Miriam Street



Project is under construction, to be completed late 2013.




 

University Drive @ 70th



Project is under design.  Construction to begin late 2013.

 

 

Fairfield Avenue



Project design is completed.  Construction is to begin after second bond sale.

.

 

Lewis Place/Carver



Project is currently bidding.  Construction is to begin late 2013.




 

Brealock Drive

Project is currently under design, to be completed late 2013.  Construction will begin after second bond sale or as funds become available.




 

Woodmont Avenue



Received bids under construction.  To be completed late 2013.




 

Walker Road

Project is currently under construction. To be complete by July 2013.




 

Kingston Road

Project design is completed. Construction is to begin after second bond sale or as funds become available.




 

Mackey Lane



Project is currently under construction. To be complete by July2013.




 

South Kirkwood

Project is under design. Construction is to begin after second bond sale or as funds become available.




 

Stoner Avenue



Project is currently under construction. To be complete by April 2013.




 

C.E. Galloway

Project is under design.  Construction is to begin after second bond sale.




 

Oakdale

Design to go through A/E Selection.  Construction is to begin after second bond sale.




 

Elvis Presley Blvd Median



Project is under design. Construction is to be completed by September 2013.




 

Rosary Lane Sidewalk



Project has been completed.




 

Zeke Street



Project to go through A/E Selection.  This project is for design only.




 

Greenway Street

Project to go through A/E Selection.  Design and construction to begin after second bond sale.




 

Midway Avenue

Project has been bid. Construction underway by July 2013.




 

Missouri Avenue

Project is under design.  Construction to begin after second bond sale.




 

Jewella Avenue

Project has been bid. Construction underway by July 2013.




 

Lakeshore Drive

Project is under construction, to be complete by Aug. 2013.




 

Woolworth Road

Project is under design.  Construction to begin after second bond sale.




 

Scenic @ Tierra

Project has been completed.




 

Holcomb Street

Project is currently bidding. Construction to begin mid 2013.




 

Ackard Street

Project is under design.  Construction to begin following second bond sale.




 

Carroll Street

Project is ready for bids.  Construction to begin by late 2013.




 

Huntington Lane

Design is complete.  Construction to begin following second bond sale or as funds become available.




 

Grover Place

Project is under design.  Construction to begin following second bond sale or as funds become available.




 

Ashborne

Project is under design.  Construction to begin following second bond sale.




 

Village Green



Project is under design.  Construction to begin following second bond sale.






Last updated: 7/17/13


 